The
constructing contractors arrived on site in 1930 and commenced
work as soon as the state of the filled land allowed. The four
original enlisted men's barracks (Buildings 800, 802, 803, 804)
began construction in 1930, and were completed by 1932 (Figure
10). Buildings 800 and 803 were constructed according to Standard
Plan 3301-1, for 110-Man Air Corps Barracks. Buildings 802 and 804
were constructed from Standard Plan 3302-1, 200-Man Air Corps
Barracks. All were three stories, and featured rectangular floor
plans on concrete pier foundations, concrete stucco walls, and
gable-on-hip tile roofs. 92
The married Officers Quarters also
began construction in 1930, and were completed by 1932 (Figure
11). There were four Field Officers Quarters constructed according
to Standard Plan 3214-1 (Buildings 2-5), and 32 Company Officers'
Quarters (Standard Plan 3215-1, Buildings 7-12, 15-18, 20, 22,
24-43). The Officers Quarters maintained the installation's
predominant structural elements and architectural style. All 31 of
the married NCO Quarters (Standard Plan 3216-1, Buildings 200-230)
were finished in 1932, on schedule with the rest of the housing
units, and featured structural elements and architectural style
similar to the Officers Quarters (Figure 12). The primary
difference was that they were intended to house two NCO families
in a duplex layout, whereas Officer Quarters housed only a single
family.93

|
Figure
10 - Albrook
Building 802, 200-Main Air Corps Barracks |
Figure
11 - Albrook Building 4, Field Officer's Quarters |
Figure
12 - Albrook
Building 205, NCO Duplex Quarters (Source of
three photos: War Department Q.M.C. Form 117, Real Estate
Office, Howard AFB, RoP) |
The Open Mess (Building 13, now the
Bachelor Officers' Quarters (BOQ)) was also completed in 1932.
This two-story structure featured structural elements and
architectural style similar to the Officer and NCO housing units
(Figure 13). It included 16 two-room quarters on the second floor,
along with a common dining room, library, and billiard room.
Servants rooms and a garage originally occupied the first floor.
94
The machine shop and warehouse (Buildings 401 and 402) were
constructed according to the Quartermaster Corps Construction
Division's Standard Plan 695-250 (Figure 14).95
 |
Figure
13 - Albrook
Building 13, Bachelor Officers' Quarters |
Figure
14 - Albrook
Building 402, Air Corps Warehouse |
Figure
15 - Albrook
Building 444, Air Corps 1930-B Design hangar (Source
of three photos: War Department Q.M.C. Form 117, Real
Estate Office, Howard AFB, RoP) |
Only three of the four planned
hangars were actually constructed, due to funding shortages.
Contracts were not let for Hangars No. 2 and 3 (Buildings 445 and
446) until early 1931, as additional filling work had to be
completed before construction could begin, and extra time allowed
for settling. Hangar No. 1 (Building 444) began even later in
1931, because special drainage facilities had to be completed to
allow for the diversion of the Maria Sala River which ran directly
behind its proposed site (Figure 15).
Nevertheless, all three hangars
were completed by the end of 1932 (Figure 16). These double
hangars were constructed according to an Air Corps standard plan
(1930-B Design) that found wide-spread use in the continental U.S.
in other expansion projects associated with the Five-Year Program.
The hangars were fronted by large concrete warm-up aprons that
measured 400 x 150 feet. These aprons were constructed to allow
for the simultaneous preparation of an entire squadron of pursuit
aircraft, but were also designed to support the weight of a loaded
bomber of the type employed by the Air Corps at that time. Wheel
loadings of the design also called for the aprons to be able to
support the weight of a fully-loaded fuel truck, at 7.5 tons.
Shortly after their completion in 1932, the two aprons were
connected by a 50-foot wide concrete strip, providing an emergency
landing area that measured 950 x 50 feet which would remain clear
and dry even in adverse weather (Figure 17).96
By April 1932, this original
construction program was complete. All the necessary housing
facilities were ready to accept personnel, and the flightline had
received the hangars necessary to support regular flying
operations. The field itself still needed a good deal of drainage
work to allow for all weather flying, and the new Bermuda grass
surface had yet to be completed in order to keep down the native
grasses. Nevertheless, in April 1932, Albrook field was surveyed,
its boundaries were marked off as an official Field Reservation,
and it was commissioned as an active air field. Active units at
this time were the 44th Observation Squadron, the 7th Squadron,
and the 25th Bombardment 97 Squadron.97
(Above) Figure 16
- Albrook Buildings 444 (Hangar #1) and 445 (Hangar 2), ca. 1934 (Source both photos: History
Office, Howard AFB, RoP)
|
|
 |
(Right)
Figure
17 - Albrook
Field flight line showing parking aprons and connecting
emergency landing strip, 21 August 1937. |
Early Improvements
Before other operational units
could arrive, more work had to be done to the flying field to
allow its use during rainy weather. Besides this field work,
little other new construction was accomplished before the build-up
prior to World War II. Throughout the mid-1930s, very little
funding support was available for expansion of base facilities,
and the Air Corps had to make do with what it had. New
construction was limited to seven buildings that had been left out
of the original construction program. In addition, a good deal of
landscaping had yet to be completed, and this apparently posed
some real problems. The original personnel at Albrook were having
trouble keeping the landscape vegetation alive, as the soil that
had been used for fill was infertile. Major E. A. Lohman
assigned a set group of numbered palm trees to each officer on
base. He told them that they were to guard and tend the trees, and
that if any of their trees died, they would be summarily
court-martialed. The presence of the thriving palms at Albrook
today speaks volumes for the officers' dedication, and perhaps
their fear that Major Lohman meant what he said.98
Improvements to the flying field
itself were needed as soon as Albrook was commissioned. As early
as 1931, the Departmental Commander, General Preston Brown had
stated that concrete runways situated in the direction of the
prevailing winds would be absolutely necessary in order to render
Albrook Field safe for all-weather flying operations. This request
was echoed on a yearly basis by the a succession of Albrook's base
commanders, beginning with Major Lohman. These requests met with
repeated rebuttals from the Air Corps and the War Department, on
the basis that funds were simply not available for the improvement
of a newly commissioned airfield. More time was to be given to see
if the sod field might possibly be improved enough to allow for
efficient flying operations. Some additional improvements were
made to the drainage system during the period, but they never
successfully corrected the essential flaws in the field that
resulted from the constant uneven settling and slow drainage
during rainy weather. In the end, it was not until 1938 that
Congress approved funding for the construction of a paved runway
at Albrook, which was finally completed only in April 1939.99
(Footnotes and
bibliography are at the end of this
section)